Memorial Field variance request approved

On Jan. 30, the Glen Ellyn Village Board unanimously approved the Memorial Field variance requests for the following site improvements:
  • Field lighting, which includes six light poles (two 60’ poles and four 70’ poles) with shielded light fixtures
  • Third base sideline sidewalk/ramp
  • North side bleachers with improved handicap accessibility (Bleacher capacity of 240)
  • Masonry fence along the north side of the field
  • Batting cage renovations
  • Glenbard District 87 responded to residents’ concerns and adjusted the usage request to the Glen Ellyn Plan Commission, based on community feedback, as follows:
  • No third-party rentals (light use)
  • No summer light use (June 1 – Aug. 14)
  • No weekend light use
  • No winter light use
  • No morning light use prior to school
  • No light use after 9 p.m.
  • Create an advisory group consisting of Glenbard West administration, village representative and neighbors to review the use of lights
  • Next steps:
  • Glenbard District 87 will hold a public hearing on Feb. 27.  The time and location of the hearing will be publicized.
  • Launch community fund raising effort related to lights at Memorial Field.  The lights will be 100% funded by community contributions.
  • Project timeline:
  • 2/27/2012               District 87 public hearing
  • 2/2012 – 3/2012       Community fundraising effort
  • 3/31/2012               100% of light project funds raised, deposited (target)
  • 4/2012          District 87 Board discussion/authorization to bid
  • If District 87 Board of Education approves:
  • 5/23/2012               Bid documents 100% complete, issued
  • 6/13/2012               Bid opening
  • 6/25/2012               District 87 Board discussion
  • 7/9/2012                District 87 Board approval of construction contract
  • 7/13/2012               Construction starts
  • 8/17/2012               Substantial completion
  • 8/31/2012               Final Completion – Glenbard West use for 2012-2013 year